Slide background
Slide background
Slide background
Slide background
Slide background
Slide background

2/1/21 Project Update to City of Roseville and PCTPA

On February 2, 2021, CCJPA presented an update on the Sacramento to Roseville Third Track project to the City of Roseville and the Placer County Transportation Planning Agency (PCTPA). The presentation slides can be accessed here: http://sactoroseville3rdtrack.com/wp-content/uploads/2021/02/CCJPA-City-PCTPA_Mtg_20210201.pdf

By |February 12th, 2021|Categories: Uncategorized|Tags: |0 Comments

11/18/20 Board Update

An update on the Sacramento to Roseville Third Track project was presented to the CCJPA Board of Directors on November 18, 2020. The presentation slides can be accessed here: http://sactoroseville3rdtrack.com/wp-content/uploads/2020/11/CCJPA_Board_Mtg_20201118.pdf.

By |November 20th, 2020|Categories: Uncategorized|Tags: |0 Comments

11/20/19 Board Update

An update on the Sacramento to Roseville Third Track project was presented to the CCJPA Board of Directors on November 20, 2019. The presentation slides can be accessed here: http://sactoroseville3rdtrack.com/wp-content/uploads/2019/12/CCJPA_Board_Mtg_20191120.pdf.

By |January 2nd, 2020|Categories: Uncategorized|Tags: |0 Comments

Field Investigations and Initial Design Submittals Completed

Geotechnical investigations and materials testing/disposal of geotechnical boring drill spoils have all been completed. 88 borings ranging from 10’ to 100’ deep were drilled along the 10-mile long corridor. Geotechnical recommendations for trackwork, sitework, and structures are under development.

Ground survey, supplementing aerial survey mapping, was completed.

The CCJPA/TranSystems team have continued ongoing coordination with project partners: Union Pacific Railroad, the City of Roseville, Placer County Transportation Planning Agency, Amtrak, and others. Preliminary designs have been developed and refined. The Union Pacific Railroad Dry Creek Bridge concept submittal and the 25% design submittal packages have been completed.

By |September 23rd, 2019|Categories: Uncategorized|Tags: |0 Comments

Field Investigations Underway

Field investigations for the Sacramento to Roseville Third Track Project – Phase 1 have been underway. Under TranSystems’ final engineering design contract, ground surveying is being done to supplement the aerial survey that was previously flown. Geotechnical investigation work has also been proceeding along the approximately 10 mile-long corridor between around Watt Avenue in Sacramento County and East Roseville Parkway in Roseville. These field investigations support the engineering design work that will reach the 25% complete level in early 2019.

By |December 27th, 2018|Categories: Uncategorized|Tags: |0 Comments

10% Design Completed

As the design work for the Sacramento to Roseville Third Track Phase 1 starts up, the CCJPA/TranSystems team have had initial meetings with various stakeholders: Union Pacific Railroad (UP), the City of Roseville, and Amtrak, in order to discuss the project, collect data, and start early coordination about facilities needs and layout. Initial outreach to utility companies that may have facilities within the bounds of the project have been contacted, in order that they may provide information on their existing facilities.

In early July, a 10% design submittal package was submitted for CCJPA and UP review. Once approved, the 10% submittal will become the basis for development of the 25% design submittal.

By |August 27th, 2018|Categories: Uncategorized|Tags: |0 Comments

Project Update to PCTPA

On May 23, 2018, CCJPA met with the Placer County Transportation Planning Agency (PCTPA) Board to provide an update on the Sacramento to Roseville Third Track Project. Phase 1 is anticipated to increase service to Placer County. The project update can be viewed here.

By |August 27th, 2018|Categories: Uncategorized|Tags: |0 Comments

Phase I Design Kick-Off Meeting

The Sacramento to Roseville Third Track Project has reached an exciting milestone! On Tuesday, February 13, 2018, the Capitol Corridor and the engineering firm, TranSystems, met to kick off the design stage of Phase I of the project, which will ultimately add two more round trips between Sacramento and Roseville.

Phase I of the Sacramento to Roseville project will cost just under $90M and will take approximately 4-5 years, with the first two years being dedicated to the design phase, followed by 2-3 years of construction.

We are thrilled to be working with TranSystems to bring this vital expansion project closer to reality.

By |April 20th, 2018|Categories: Uncategorized|Tags: |0 Comments

CCJPA Board Approves Project & Certifies Final EIR

On Wednesday, November 18 the CCJPA Board of Directors reached a significant milestone for the Sacramento to Roseville Third Track Project. The Board certified the Final Environmental Impact Report (EIR) and approved the project. This Record of Decision brings the Capitol Corridor and their partner agencies one step closer to seeing increased service between Sacramento and Roseville. The next step for CCJPA is to finalize the Environmental Assessment (EA) for approval by the Federal Railroad Administration (FRA).

By |November 19th, 2015|Categories: Uncategorized|Tags: |0 Comments

Notice of Availability of Final Environmental Impact Report (EIR)

On Wednesday, November 4, 2015, CCJPA ― Lead Agency for the California Environmental Quality Act (CEQA) ― made the Final Environmental Impact Report (EIR)/Responses to Comments for its proposed Third Track Project available to the public. The Final EIR and other project documents may be viewed from the website under the Documents page. Interested parties may also review a copy of the final documents at various public counter locations. Click on the Public Involvement  page for more information.

By |November 4th, 2015|Categories: Uncategorized|Tags: |0 Comments